RCC M25 in foundation

REF-4.1.8 · per

Derived rate

₹7,914.30

Materials

ResourceCoeff.UnitRateAmount
Cement OPC 43 7.7 bag 390 3,003
Coarse aggregate 20 mm 0.88 cum 1,450 1,276
Fine aggregate (sand) 0.44 cum 1,650 726

Labour

ResourceCoeff.UnitRateAmount
Mason (skilled) 0.9 day 850 765
Helper (unskilled) 1.6 day 620 992

Plant

ResourceCoeff.UnitRateAmount
Concrete mixer 0.4 m³ 0.1 day 1,200 120
Base (materials + labour + plant)₹6,882.00
Overheads & profit15%
Derived rate₹7,914.30

Where this comes from: reference rates from real, live projects. Indicative — verify before tender.

About rate analysis

What is rate analysis?
Rate analysis breaks a unit rate into its underlying material, labour and plant resources with coefficients, so you can see exactly how the rate is built up and adjust it for your project.
Where do the resource rates come from?
From real, live construction projects. They are indicative — adjust for local market conditions before tender.