Sample Bill of Quantities — India
A complete, sectioned and costed BOQ — every quantity, rate and amount, with a grand total. This is exactly what Construction Tools produces from a plain-English brief. Rates referenced from real, live projects.
Sample BOQ — G+2 · 4,500 sq ft · residential
Rates from reference rates from real, live projects
· 46 lines · 10 sections
What this sample assumes (your own brief drives your numbers)
- 1500 sqft per floor × 3 floors = 4500 sqft total built-up area
- Brick masonry assumed as 230mm thick burnt clay brick walls for external and 115mm for internal partitions
- Vitrified tile flooring assumed 600×600mm tiles in all rooms
- Standard finishes assumed as internal cement plastering with putty and emulsion paint
- External finish assumed as sand-faced cement plastering with exterior emulsion paint
- Basic electrical assumed as concealed copper wiring with standard switches, one DB per floor, adequate light and power p
- Basic plumbing assumed as CPVC for hot water, uPVC for cold water supply, and PVC for drainage
- Foundation assumed as isolated RCC footings on medium soil with safe bearing capacity of 150 kN/sqm
- Roof assumed as RCC flat slab with waterproofing treatment on terrace
- Staircase assumed as RCC dog-legged type
- Bathroom and kitchen wall tiles assumed up to 7 ft height with ceramic tiles
- Windows assumed as aluminium sliding type with 5mm clear glass
Substructure ₹13,24,471.10
| Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|
| Anti-termite treatment to soil under foundation, plinth, and floors using approved chemicals as per IS 6313 (Part II) 2.01 high | m² | 418 | 101.50 | 42,427.00 |
| Earthwork excavation in foundation trenches for RCC framed structure including disposal of surplus soil within site 2.02 high | m³ | 210 | 366.86 | 77,040.60 |
| Filling in plinth with selected earth, watering, compaction, and dressing up to required levels 2.03 high | m³ | 60 | 248.00 | 14,880.00 |
| Providing and laying Plain Cement Concrete (PCC) 1:4:8 in foundations and under floors as per IS 456 2.04 high | m³ | 42 | 4,786.10 | 2,01,016.20 |
| RCC M20 grade for footings, plinth beams, and columns up to plinth level including shuttering and finishing 2.05 high | m³ | 55 | 6,366.00 | 3,50,130.00 |
| Supplying and fixing TMT Fe500D reinforcement for substructure including cutting, bending, binding, and placing in position 2.06 high | kg | 8,250 | 75.45 | 6,22,462.50 |
| Brick masonry in cement mortar 1:6 for foundation and plinth walls using class 1 bricks 2.07 high | m³ | 38 | 434.60 | 16,514.80 |
Superstructure ₹27,30,441.13
| Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|
| RCC M25 grade for columns, beams, slabs, and staircases above plinth level including shuttering and finishing 3.01 high | m³ | 175 | 2,472.11 | 4,32,619.25 |
| Supplying and fixing TMT Fe500D reinforcement for superstructure including cutting, bending, binding, and placing in position 3.02 high | kg | 26,250 | 75.45 | 19,80,562.50 |
| Brick masonry in cement mortar 1:6 for walls above plinth level using class 1 bricks 3.03 high | m³ | 120 | 428.80 | 51,456.00 |
| Brick masonry in cement mortar 1:4 for partition walls in kitchens, bathrooms, and bedrooms 3.04 high | m³ | 38 | 1.15 | 43.70 |
| Providing and fixing precast RCC lintels and sills over doors, windows, and ventilators 3.05 high | m³ | 6 | 7,951.88 | 47,711.28 |
| Providing and fixing RCC staircase including finishing, nosing, and handrail base 3.06 high | m³ | 12 | 13,266.80 | 1,59,201.60 |
| Providing and fixing RCC parapet walls and balcony projections as per architectural drawings 3.07 high | m³ | 8 | 7,355.85 | 58,846.80 |
Waterproofing & Damp Proofing ₹2,07,994.50
| Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|
| Waterproofing treatment to terrace slab with two coats of polymer modified cement slurry and protective screed 4.01 high | m² | 150 | 996.00 | 1,49,400.00 |
| Waterproofing treatment to balconies and bathrooms with chemical coating and screed as per reference rates specifications 4.02 high | m² | 90 | 519.00 | 46,710.00 |
| Damp proof course (DPC) 40 mm thick with cement mortar 1:2 and waterproofing compound at plinth level 4.03 high | m² | 45 | 264.10 | 11,884.50 |
Doors, Windows & Joinery ₹10,02,457.50
| Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|
| Providing and fixing flush doors with hardwood frame and ISI marked fittings including painting/polishing 6.01 high | m² | 110 | 2,819.25 | 3,10,117.50 |
| Providing and fixing UPVC windows with double glazing and ISI marked hardware 6.02 high | m² | 95 | 5,060.00 | 4,80,700.00 |
| Providing and fixing ventilators with aluminum frame and glass panels including mosquito mesh 6.03 high | m² | 18 | 5,102.50 | 91,845.00 |
| Providing and fixing stainless steel railing for staircase and balconies including supports and brackets 6.04 high | rm | 65 | 1,843.00 | 1,19,795.00 |
Finishes ₹24,69,620.00
Plumbing & Sanitary ₹0.00
Electrical & ELV ₹0.00
Lifts & Vertical Transportation ₹0.00
External Development ₹0.00
Common Areas & Amenities ₹0.00
Locked rows show what a full BOQ contains — the first 25 of 46 lines are priced in this preview. Generate your own BOQ to price every line. Rates are indicative, referenced from real, live projects; verify against current market rates before tender.
About this sample BOQ
- Is this a real, costed sample BOQ?
- Yes — it is a complete, sectioned BOQ generated by Construction Tools from a typical India project brief, with a quantity and rate on every priced line. Numbers are indicative, referenced from real, live projects; verify against current market rates before tender.
- What sections does a BOQ include?
- This sample covers 10 sections — Substructure, Superstructure, Waterproofing & Damp Proofing, Doors, Windows & Joinery, Finishes, Plumbing & Sanitary, Electrical & ELV, Lifts & Vertical Transportation, External Development, Common Areas & Amenities — across 46 line items. Your own project's sections will vary with scope and site conditions.
- Can I make my own BOQ like this?
- Yes. Open the BOQ Generator, describe your project in plain English, and get your own complete, costed BOQ in about a minute — the first 25 lines priced free.
- How accurate are the BOQ numbers?
- Rates are indicative, referenced from real, live projects. Use them for early-stage budgeting and feasibility, and verify against current market rates before tender.