7.62 cm thick brick wall laid in cement stone dust (from crusher) mortar 1:4 with every…
Indicative unit rate and the full material, labour and plant build-up — per m².
7.62 cm thick brick wall laid in cement stone dust (from crusher) mortar 1:4 with every…
per m²
Indicative unit rate
₹53.50
per m²
Materials
| Resource | Coeff. | Unit | Rate | Amount |
|---|---|---|---|---|
| Common burnt clay bricks (modular, IS:1077) | 40 | Nos | 0.35 | 14 |
| Cement (OPC 43 grade, IS:8112) | 3.2 | kg | 7 | 22.4 |
| Stone dust (crusher, IS:383) | 12.8 | kg | 0.3 | 3.84 |
| Hoop iron strip (IS:432, 25mm x 1.6mm) | 1.2 | Rmt | 2 | 2.4 |
Labour
| Resource | Coeff. | Unit | Rate | Amount |
|---|---|---|---|---|
| Mason 1st class | 0.09 | day | 476 | 4.28 |
| Beldar | 0.12 | day | 320.83 | 3.85 |
| Bhisti | 0.03 | day | 320.83 | 0.96 |
Plant
No plant component for this item.
Where this comes from: reference rates from real, live projects. Indicative for early-stage estimating — verify before tender.
Need more than one rate?
Build a full BOQ with every item priced, or open this item in EstimateNext.
Looking for something else? Search all items →
About this rate
- How is the rate for 7.62 cm thick brick wall laid in cement stone dust (from crusher) mortar 1:4 with every… calculated?
- It is built up from the material, labour and plant resources shown, with reference rates from real, live projects. Figures are indicative — verify against current market rates before tender.
- What is the unit of measurement?
- The rate of ₹53.50 is per m². Multiply by your quantity to estimate the line total.