Earth work in filling in foundation trenches or plinth with good earth, in layers not ex…
Indicative unit rate and the full material, labour and plant build-up — per % cum.
Earth work in filling in foundation trenches or plinth with good earth, in layers not ex…
per % cum
Indicative unit rate
₹49,179.00
per % cum
Materials
| Resource | Coeff. | Unit | Rate | Amount |
|---|---|---|---|---|
| Good earth (carried from borrow area) | 100 | cum | 350 | 22,864.11 |
| Truck 10 T charges (lead up to 1 km) | 12 | hour | 474.3 | 3,718.1 |
| Fuel charges for transport | 12 | hour | 497.1 | 3,896.83 |
Labour
| Resource | Coeff. | Unit | Rate | Amount |
|---|---|---|---|---|
| Mason 1st class | 3 | day | 816 | 1,599.18 |
| Beldar | 10 | day | 736 | 4,808 |
Plant
No plant component for this item.
Where this comes from: reference rates from real, live projects. Indicative for early-stage estimating — verify before tender.
Need more than one rate?
Build a full BOQ with every item priced, or open this item in EstimateNext.
Looking for something else? Search all items →
About this rate
- How is the rate for Earth work in filling in foundation trenches or plinth with good earth, in layers not ex… calculated?
- It is built up from the material, labour and plant resources shown, with reference rates from real, live projects. Figures are indicative — verify against current market rates before tender.
- What is the unit of measurement?
- The rate of ₹49,179.00 is per % cum. Multiply by your quantity to estimate the line total.