Labour charges for wrought and put up including fixing in position for Teak wood Flush t…
Indicative unit rate and the full material, labour and plant build-up — per m².
Labour charges for wrought and put up including fixing in position for Teak wood Flush t…
per m²
Indicative unit rate
₹1,151.00
per m²
Materials
| Resource | Coeff. | Unit | Rate | Amount |
|---|---|---|---|---|
| Teak wood in planks for flush door shutter 35mm thick | 1 | sqm | 650 | 464.4 |
| Teak wood in scantling for door frame | 4 | Rmt | 90 | 257.21 |
| Adhesive (phenol formaldehyde resin) | 0.3 | kg | 120 | 25.72 |
| Iron screws (50mm) | 0.05 | kg | 80 | 2.86 |
| Carriage of teak wood (planks & scantling) | 0.05 | cum | 121.29 | 4.33 |
Labour
| Resource | Coeff. | Unit | Rate | Amount |
|---|---|---|---|---|
| Carpenter 2nd class | 0.8 | day | 374.5 | 214.05 |
| Beldar | 0.4 | day | 320.83 | 91.69 |
Plant
No plant component for this item.
Where this comes from: reference rates from real, live projects. Indicative for early-stage estimating — verify before tender.
Need more than one rate?
Build a full BOQ with every item priced, or open this item in EstimateNext.
Looking for something else? Search all items →
About this rate
- How is the rate for Labour charges for wrought and put up including fixing in position for Teak wood Flush t… calculated?
- It is built up from the material, labour and plant resources shown, with reference rates from real, live projects. Figures are indicative — verify against current market rates before tender.
- What is the unit of measurement?
- The rate of ₹1,151.00 is per m². Multiply by your quantity to estimate the line total.