Preparation of plastered or concrete surfaces for painting, including sand papering the…
Indicative unit rate and the full material, labour and plant build-up — per do.
Preparation of plastered or concrete surfaces for painting, including sand papering the…
per do
Indicative unit rate
₹11.15
per do
Materials
| Resource | Coeff. | Unit | Rate | Amount |
|---|---|---|---|---|
| Sand paper No. 120 | 1 | sqm | 0.8 | 0.39 |
| Raw linseed oil, IS:75 | 0.03 | litre | 110 | 1.59 |
| Approved quality filler (white lead, linseed oil, varnish, chalk mitti) | 0.05 | kg | 80 | 1.93 |
Labour
| Resource | Coeff. | Unit | Rate | Amount |
|---|---|---|---|---|
| Painter 1st class | 0.02 | day | 476 | 4.59 |
| Beldar | 0.01 | day | 320.83 | 1.55 |
Plant
No plant component for this item.
Where this comes from: reference rates from real, live projects. Indicative for early-stage estimating — verify before tender.
Need more than one rate?
Build a full BOQ with every item priced, or open this item in EstimateNext.
Looking for something else? Search all items →
About this rate
- How is the rate for Preparation of plastered or concrete surfaces for painting, including sand papering the… calculated?
- It is built up from the material, labour and plant resources shown, with reference rates from real, live projects. Figures are indicative — verify against current market rates before tender.
- What is the unit of measurement?
- The rate of ₹11.15 is per do. Multiply by your quantity to estimate the line total.