Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing i…

Indicative unit rate and the full material, labour and plant build-up — per kg.

Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing i…

per kg

Indicative unit rate

₹427.25

per kg

Materials

Resource Coeff. Unit Rate Amount
TMT steel bars Fe-500 grade conforming to IS 1786 1 kg 370 370
Binding wire 18 SWG (for tying reinforcement) 0.01 kg 700 5.6

Labour

Resource Coeff. Unit Rate Amount
Mason 1st class (for cutting, bending, placing, binding) 0.03 day 476 14.28
Beldar (for assisting in handling and placing steel) 0.03 day 320.83 8.02

Plant

No plant component for this item.

Where this comes from: reference rates from real, live projects. Indicative for early-stage estimating — verify before tender.

Need more than one rate?

Build a full BOQ with every item priced, or open this item in EstimateNext.

Looking for something else? Search all items →

About this rate

How is the rate for Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing i… calculated?
It is built up from the material, labour and plant resources shown, with reference rates from real, live projects. Figures are indicative — verify against current market rates before tender.
What is the unit of measurement?
The rate of ₹427.25 is per kg. Multiply by your quantity to estimate the line total.