Skip to content
ConstructionTools by SoftNext Solutions

Providing and fixing flooring with full depth jointing and pointing to the Vitrified/ Ce…

Indicative unit rate and the full material, labour and plant build-up — per m².

Providing and fixing flooring with full depth jointing and pointing to the Vitrified/ Ce…

per m²

Indicative unit rate

₹373.00

per m²

Materials

Resource Coeff. Unit Rate Amount
Epoxy emulsion grout (for jointing and pointing of tiles, 3-5 mm width) 0.35 kg 420 87.87
Synthetic/resin adhesive (for fixing tiles, excluding cost of tiles) 1.2 kg 85 60.97
Nylon spacers (3-5 mm width, for tile joints) 10 nos 1 5.98

Labour

Resource Coeff. Unit Rate Amount
Mason 1st class (for laying and jointing tiles) 0.2 day 893 106.76
Beldar (for assisting in laying, cleaning, and finishing) 0.15 day 805 72.18

Plant

No plant component for this item.

Where this comes from: reference rates from real, live projects. Indicative for early-stage estimating — verify before tender.

Need more than one rate?

Build a full BOQ with every item priced, or open this item in EstimateNext.

Looking for something else? Search all items →

About this rate

How is the rate for Providing and fixing flooring with full depth jointing and pointing to the Vitrified/ Ce… calculated?
It is built up from the material, labour and plant resources shown, with reference rates from real, live projects. Figures are indicative — verify against current market rates before tender.
What is the unit of measurement?
The rate of ₹373.00 is per m². Multiply by your quantity to estimate the line total.
Chat on WhatsApp