Sample Bill of Quantities — United Kingdom

A complete, sectioned and costed BOQ — every quantity, rate and amount, with a grand total. This is exactly what Construction Tools produces from a plain-English brief. Rates referenced from real, live projects.

Sample BOQ — G+1 · 280 m² · residential Rates from reference rates from real, live projects · 48 lines · 7 sections
What this sample assumes (your own brief drives your numbers)
  • built_up_area calculated as 140 sqm per floor × 2 floors = 280 sqm total
  • Pitched roof with concrete interlocking tiles assumed as standard UK detached house
  • Timber trussed rafter roof structure assumed
  • Strip foundations assumed for load-bearing masonry walls
  • Upper floor assumed to be timber joist construction
  • Standard finishes interpreted as plaster skim walls, emulsion paint, carpet/vinyl flooring, ceramic tiled bathrooms and
  • Basic electrics interpreted as standard domestic lighting, sockets, consumer unit, and smoke/heat detectors to current B
  • Basic plumbing interpreted as one kitchen, one downstairs WC, one family bathroom, and one en-suite
  • Gas central heating with combi boiler assumed
  • uPVC double-glazed windows and composite external doors assumed
  • Standard drainage to mains sewer assumed
  • No garage, conservatory, or outbuildings included
Preliminaries £2,264.76
Preliminaries line items
Description Unit Qty Rate Amount
Contractor's general overheads, site establishment, insurances, and management for the duration of the works, including temporary accommodation, welfare, and statutory obligations
1.01
L S 1 1,225.00 1,225.00
Temporary fencing and hoarding to site perimeter, including gates and access control, maintained for contract period
1.03
m 80 3.08 246.40
Scaffolding, access towers, and working platforms to all elevations and roof areas for construction and finishing works
1.04
L S 1 3.36 3.36
Temporary services to site, including water, electricity, and drainage, for construction use
1.05
L S 1 790.00 790.00
Substructure £112,781.80
Substructure line items
Description Unit Qty Rate Amount
Excavation in trenches for strip foundations, not exceeding 1.5m deep, including disposal of surplus soil off site
2.01
70 380.00 26,600.00
Concrete strip foundations, in-situ, C25/30, 600mm wide x 225mm thick, including compacting and curing
2.02
38 380.00 14,440.00
Damp proof membrane, 1200 gauge polythene, under ground floor slab, lapped and sealed at joints
2.03
140 3.60 504.00
Reinforced concrete ground floor slab, in-situ, C30/37, 150mm thick, including mesh reinforcement, compacting and curing
2.04
140 147.50 20,650.00
Blinding layer, sand/cement, 50mm thick, under slab
2.05
140 6.78 949.20
Engineering brickwork to foundation walls, below DPC, 215mm thick, in English bond, including mortar
2.06
60 187.31 11,238.60
Horizontal damp proof course, 150mm above ground level, to all external and internal walls
2.07
m 120 320.00 38,400.00
Superstructure £131,124.75
Superstructure line items
Description Unit Qty Rate Amount
External cavity wall construction, 102.5mm facing brick outer leaf, 100mm full-fill cavity insulation, 100mm blockwork inner leaf, including wall ties and stainless steel lintels
3.01
320 160.00 51,200.00
Internal loadbearing blockwork partitions, 100mm thick, medium density, including mortar
3.02
180 56.00 10,080.00
Internal non-loadbearing stud partitions, 75mm metal studs, 2 layers 12.5mm plasterboard each side, including insulation
3.03
90 75.00 6,750.00
Precast concrete upper floor slabs, 200mm thick, including mesh reinforcement and grouting joints
3.04
140 119.50 16,730.00
Structural steel beams and lintels to support openings, including fire protection
3.05
tonne 2.5 375.73 939.33
Timber roof structure, softwood trussed rafters, purlins, wall plates, and bracing, complete
3.06
140 49.00 6,860.00
Roof covering, concrete interlocking tiles, including underlay, battens, and all necessary flashings
3.07
160 29.80 4,768.00
Rainwater goods, uPVC gutters and downpipes, including brackets and fittings
3.08
m 60 32.49 1,949.40
uPVC double glazed windows, including sills, ironmongery, and complete installation
3.09
38 260.00 9,880.00
External doors, composite insulated, including frames, ironmongery, and weather seals
3.10
no 4 693.01 2,772.04
Balcony/terrace waterproofing, liquid applied membrane system, including upstands and outlets
3.12
18 106.84 1,923.12
Stainless steel and glass balustrades to balconies and stairs, including fixings
3.13
m 22 785.13 17,272.86
Internal Finishes £9,294.80
Internal Finishes line items
Description Unit Qty Rate Amount
Cement:sand screed, 50mm thick, to ground and upper floors, trowelled smooth, ready to receive floor finishes
4.01
280 21.71 6,078.80
Ceramic floor tiles, 450x450mm, to kitchen, bathrooms, and utility areas, including adhesive and grout
4.02
48 67.00 3,216.00
Laminate timber flooring to bedrooms and living areas, including underlay and trims
4.03
120
Carpet tiles to corridors, lobby, and gym, including underlay and edge strips
4.04
32
Wall tiling, ceramic, 200x300mm, to bathrooms and kitchen splashbacks, including adhesive and grout
4.05
52
Plaster skim coat to internal walls and ceilings, 2mm thick, ready for decoration
4.06
900
Emulsion paint to walls and ceilings, two coats, white or pastel shade
4.07
900
Gloss paint to internal timber and metalwork, two coats, including preparation
4.08
90
External Works £0.00
External Works line items
Description Unit Qty Rate Amount
Paved driveway and parking area, 60mm thick concrete block paving on sand bed, including edge restraints
7.01
60
Footpaths around building, 900mm wide, 50mm thick concrete paving slabs on sand/cement bed
7.02
40
Soft landscaping, turfing, planting beds, shrubs, and trees, including topsoil and mulching
7.03
110
Boundary fencing, timber close boarded, 1.8m high, including posts and gravel boards
7.04
m 80
Surface water drainage, uPVC gullies, channels, and below ground pipework to soakaway
7.05
L S 1
External electrical supply for garden and outbuildings, including armoured cabling and weatherproof sockets
7.08
L S 1
Fittings and Furnishings £0.00
Fittings and Furnishings line items
Description Unit Qty Rate Amount
Fitted kitchen units, base and wall cupboards, post-formed worktops, including all ironmongery and soft-close hinges
5.01
L S 1
Services £0.00
Services line items
Description Unit Qty Rate Amount
Sanitary installations, including WCs, basins, baths, showers, taps, traps, and all accessories to bathrooms and cloakrooms
6.01
L S 1
Hot and cold water supply, including pipework, valves, insulation, and connections to all sanitary fittings
6.02
L S 1
Soil and waste water drainage, including uPVC pipework, vent pipes, and connections to main drain
6.03
L S 1
Heating installation, gas-fired condensing boiler, radiators, pipework, controls, and commissioning
6.04
L S 1
Electrical installation, including mains distribution board, sub-circuits, lighting, power sockets, and earthing
6.06
L S 1
Fire alarm and detection system, addressable, with smoke/heat detectors, sounders, and manual call points
6.08
L S 1
Lift installation, 8-person passenger lift, electric traction, 2 stops, including shaft, doors, and controls
6.10
no 1
Service lift (dumbwaiter), 100kg capacity, 2 stops, including shaft and controls
6.11
no 1
Rainwater harvesting system, including collection tank, filters, pump, and distribution pipework
6.12
L S 1
Water treatment plant, compact unit, including all connections and commissioning
6.14
L S 1

Locked rows show what a full BOQ contains — the first 25 of 48 lines are priced in this preview. Generate your own BOQ to price every line. Rates are indicative, referenced from real, live projects; verify against current market rates before tender.

About this sample BOQ

Is this a real, costed sample BOQ?
Yes — it is a complete, sectioned BOQ generated by Construction Tools from a typical United Kingdom project brief, with a quantity and rate on every priced line. Numbers are indicative, referenced from real, live projects; verify against current market rates before tender.
What sections does a BOQ include?
This sample covers 7 sections — Preliminaries, Substructure, Superstructure, Internal Finishes, External Works, Fittings and Furnishings, Services — across 48 line items. Your own project's sections will vary with scope and site conditions.
Can I make my own BOQ like this?
Yes. Open the BOQ Generator, describe your project in plain English, and get your own complete, costed BOQ in about a minute — the first 25 lines priced free.
How accurate are the BOQ numbers?
Rates are indicative, referenced from real, live projects. Use them for early-stage budgeting and feasibility, and verify against current market rates before tender.